Things to do before mid-May 2017 move in.
Floors
- Replace kitchen linoleum with tile. Matching now with laundry room and bonus room. (Pic below, comes from Pacifica travertine - Ivoria Premium line.)
- Replace carpet in family room with
matching hardwoodthe same travertine tile we're using for the kitchen. This will make the house 100%matching hardwood floors for non kitchen/bathroomsa combination of the hardwood and the new tile.- Joe Ferrante is heading up this work. Demo to begin on May 5, and installation the following week.
Inspection Checklist Items
829 Seabury - HomeGuard Inspection List - from report: Home Inspection April 2017
Other
- [INQUIRY] Replace external locks
- [DONE] Wifi / Cable Hardware
- [PICKUP AFTER MOVE] Garage shelving, something like Husky 90x90
- org buckets for shelves
- [LATER] Reinforce back vine canopy? Not sure if needed, but while we're in there...
- Appliances
- Washer/Dryer
- Refrigerator
- Wire house for ethernet. Worth doing anything now while we're rooting around?
Utilities
- [SCHEDULED] Comcast 2017-05-06 8am service cutover and onsite tech to make sure we have proper line to the junction box
- Water
- PG&E
- [INQUIRY] Garbage
- [DONE] Mail change of address for 2017-05-06
The Actual Move
- [CONFIRMED] Moving service - My Dad's Moving, for 2017-05-07
- [CONFIRMED] Walk through of old place 2017-05-10