While I picked SolarCity for a number of reasons to provide solar power, the installation timeline and process has been a bit frustrating.

  • June 10, 2017 - Submitted initial paperwork while the very professional "Energy Consultant" was on site. Paid $500 deposit and scheduled visit by an assessor to measure the roof, etc, so I could get an official proposal. Initial proposal with energy consultant ended up being the one I would want to go with (which put a set of panels on a less efficient but back roof to complement the main set of panels).