829 Seabury - Move In Checklist: Difference between revisions
From dtype.org
(→Floors: alignment) |
|||
Line 32: | Line 32: | ||
== Utilities == | == Utilities == | ||
* Comcast | * Comcast [SCHEDULED 2017-05-06] | ||
* Water | * Water | ||
* PG&E | * PG&E | ||
* Garbage | * Garbage | ||
* Mail | * Mail |
Revision as of 17:55, 25 April 2017
Things to do before mid-May 2017 move in.
Floors
- Replace carpet in family room with matching hardwood. This will make the house 100% matching hardwood floors for non kitchen/bathrooms.
- Joe Ferrante is looking at these on Apr 20.
- Replace kitchen linoleum with tile. Matching now with laundry room and bonus room. (Pic below, comes from Pacifica travertine - Ivoria Premium line.)
Inspection Checklist Items
Will get these from the HomeGuard inspection. 829 Seabury - HomeGuard Inspection List - from report: Home Inspection April 2017
Other
- [INQUIRY OUT] Replace external locks
- [ORDERED] Wifi
- [PICKUP AFTER MOVE] Garage shelving, something like Husky 90x90
- [LATER] Reinforce back vine canopy? Not sure if needed, but while we're in there...
- Appliances
- Washer/Dryer
- Refrigerator
Utilities
- Comcast [SCHEDULED 2017-05-06]
- Water
- PG&E
- Garbage